September 2023
WORK STATUS – September 2023
- Earth filling completed
- All pile foundation work completed
- Sump tank work completed
- Column raising ground floor completed
- First floor slab completed
- Column raising first floor completed
- Second floor slab completed
- Column raising second floor completed
- Third floor slab completed
- Column raising third floor completed
- Fourth floor slab completed
- Column raising fourth floor completed
- Fifth floor slab completed
- Column raising sixth slab completed
- Third floor apartment type F, E and D ceiling plastering completed
- Sump tank plastering complete up to fireroom
- 6th floor slab centering and shuttering completed
- 6th floor slab concrete completed
- 6th to 7th column raising completed
- 7th floor slab centering and shuttering completed
- 7th floor slab concrete completed
- 7th to 8th floor column raising completed
- 8th floor slab centering and shuttering completed
- 8th floor slab concrete completed
- 8th to 9th floor column raising completed
- 9th floor slab centering and shuttering completed
- 9th floor slab concrete completed
- 9th to 10th floor column raising completed
- 10th floor slab concrete completed
- 10th to 11th floor column raising completed
- 11th floor slab concrete completed
- 11th to 12th floor column raising completed
- 12th floor slab concrete completed
- 12th to 13th floor column raising completed
- 13th floor slab concrete completed
- 14th floor part 1st slab concrete completed
- 14th floor part 2nd shuttering work completed
- 14th to 15th column raising completed
- 15th floor slab concrete completed
- 16th floor slab concrete completed
- Cover slab column rising completed
- Stair roof slab in progress
MASONRY WORKS
- 3rd floor apartment ceiling plastering completed
- 4th floor apartment ceiling plastering completed
- 5th floor apartment ceiling plastering completed
- 6th floor apartment ceiling plastering completed
- 7th floor apartment ceiling plastering completed
- 8th floor apartment ceiling plastering completed
- 9th floor apartment ceiling plastering completed
- 10th floor apartment ceiling plastering completed
- 11th floor ceiling plastering completed
- 12th floor ceiling plastering completed
- 13th floor ceiling plastering completed
- 14th floor ceiling plastering completed
- 15th floor ceiling plastering in progress -50%
- 3rd floor block masonry completed
- 4th floor block masonry completed
- 5th floor block masonry completed
- 6th floor block masonry completed
- 7th floor block masonry completed
- 8th floor block masonry completed
- 9th floor block masonry completed
- 10th floor block masonry completed
- 11th floor block masonry completed
- 12th floor block masonry completed
- 13th floor block masonry completed
- 14th floor block masonry completed
- 15th floor block masonry work progressing -50%
- 3rd floor wall plastering completed
- 4th floor wall plastering work completed
- 5th floor wall plastering completed
- 6th floor wall plastering completed
- 7th floor wall plastering completed
- 8th floor wall plastering completed
- 9th floor wall plastering completed
- 10th floor wall plastering completed
- 11th floor wall plastering completed
- 12th floor wall plastering in progress -10%
ELECTRICAL WORKS
- Electrical work 3rd floor – completed
- Electrical work 4th floor-completed
- Electrical work-5th floor –completed
- Electrical work- 6th floor –completed
- Electrical work- 7th floor – completed
- Electrical work- 8th floor – completed
- Electrical work- 9th floor – completed
- Electrical work- 10th floor – completed
- Electrical work- 11th floor – completed
- Electrical work- 12th floor – completed
- Electrical work- 13th floor – 50% completed
PLUMBING WORKS
- Plumbing work 3th floor – completed.
- Plumbing work 4th floor – completed
- Plumbing work 5th floor – completed
- 3 to 9th floor core cutting and sleeve fix completed
WATERPROOFING WORKS
- 3rd floor waterproofing completed
- 4th floor waterproofing completed
- 5th floor waterproofing completed
- 6th floor waterproofing completed
- 7th floor waterproofing completed
- Waterproofing 8th floor – 50%
FIRE AND SAFETY WORK
- 3rd floor fire and safety work completed
- 4th floor fire and safety work in progress -50%
- 5th floor fire and safety work in progress -25%
- 6th floor fire and safety work completed
TILE WORK
- 3rd floor 3 F apartment toilet wall and floor tile work completed