Cordial Magnolia : Work Status

May 2024

WORK STATUS – May 2024

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Sump tank plastering complete up to fireroom
  • GF to 17th floor column raising completed
  • 1st to 16th floor slab centering and shuttering completed
  • 1st to 16th floor slab concrete completed
  • Terrace roof slab column rising completed
  • Terrace roof slab concrete completed
  • Stair roof slab completed
  • Overhead tank completed

MASONRY WORKS

  • 2nd floor plastering 50% completed
  • 3rd to 16th floor apartment ceiling plastering completed
  • 3rd to 16th floor block masonry completed
  • Terrace parapet block masonry work completed
  • 3rd to 16th floor wall plastering completed

MASONRY WORKS – OUTSIDE PLASTERING

  • South Side – ABC Outside

South side external wall plastering from 3rd to 17th floor completed

  • East Side

A, Fire Stair, F type Apartment from 3rd to 17th floor completed

  • North Side

D,E,F type Apartment from 3rd to 17th floor completed

  • West Side

C,D Type – 90% of the outside area completed

ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING

  • Electrical work 3rd to 16th floor – completed

PLUMBING WORKS

  • Plumbing work 3rd to 16th floor – completed.

WATERPROOFING WORKS

  • 3rd to 15th floor waterproofing completed
  • 16th floor waterproofing – 100% completed
  • Terrace floor – 100% completed

FIRE AND SAFETY WORK

  • 3rd to 16th floor fire and safety work completed

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor tile work completed
  • 16th floor apartments, passage, staircase – 85% completed
  • 15th floor apartments, passage, staircase – 90% completed
  • 14th floor apartments, passage, staircase – 90% completed
  • 13th floor apartments, passage, staircase – 95% completed
  • 12th floor apartments, passage, staircase – 90% completed
  • 11th floor apartments, passage, staircase – 80% completed
  • 10th floor apartments, passage, staircase – 75% completed
  • 9th floor apartments, passage, staircase – 65% completed
  • 8th floor apartments, passage, staircase – 55% completed
  • 7th floor apartments, passage, staircase – 70% completed
  • 6th floor – apartments, passage, staircase- 65% completed
  • 5th floor – apartments, passage, staircase -55% completed
  • 4th floor – apartments, passage, staircase- 60% completed
  • 3rd floor – apartments, passage, staircase- 50% completed

PAINTING WORK

  • Putty and painting work on 3F completed
  • 3rd to 4th floor putty 1st coat completed
  • 5th floor putty 1st coat 80% completed
  • 6th to 7th floor putty 1st coat completed
  • 8th floor putty 1st coat 50% completed
  • 9th to 15th floor putty 1st coat completed
  • 16th floor putty 1st coat completed
  • 16th and 15th floor A, B – 2nd coat putty completed
  • East side outside primer – completed
  • South side primer – completed
  • North side primer – completed
  • Painting interior emulsion 1st coat commenced – In Progress
  • Painting exterior emulsion 1st coat commenced – In Progress

April 2024

WORK STATUS – April 2024

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Sump tank plastering complete up to fireroom
  • GF to 17th floor column raising completed
  • 1st to 16th floor slab centering and shuttering completed
  • 1st to 16th floor slab concrete completed
  • Terrace roof slab column rising completed
  • Terrace roof slab concrete completed
  • Stair roof slab completed
  • Overhead tank completed

MASONRY WORKS

  • 2nd floor plastering 50% completed
  • 3rd to 16th floor apartment ceiling plastering completed
  • 3rd to 16th floor block masonry completed
  • Terrace parapet block masonry work completed
  • 3rd to 16th floor wall plastering completed

MASONRY WORKS – OUTSIDE PLASTERING

  • South Side – ABC Outside

South side external wall plastering from 3rd to 17th floor completed

  • East Side

A, Fire Stair, F type Apartment from 3rd to 17th floor completed

  • North Side

D, E, F type Apartment from 3rd to 17th floor completed

  • West Side

C, D Type – 90% of the outside area completed

ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING

  • Electrical work 3rd to 16th floor – completed

  PLUMBING WORKS

  • Plumbing work 3rd to 16th floor – completed.

WATERPROOFING WORKS

  • 3rd to 16th floor waterproofing completed
  • Terrace floor – 100% completed

FIRE AND SAFETY WORK

  • 3rd to 16th floor fire and safety work completed

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor tile work completed
  • 16th floor – 50% complete
  • 15th floor – 80% complete
  • 14th floor – 75% complete
  • 13th floor – 65% complete
  • 12th floor – 60% complete
  • 11th floor – 80% complete
  • 10th floor – 80% complete
  • 9th floor – 70% complete
  • 8th floor – 50% complete
  • 7th floor – 70% complete
  • 6th floor – 60% complete

PAINTING WORK

  • Putty and painting work on 3F completed
  • 3rd to 4th floor putty 1st coat completed
  • 5th floor putty 1st coat 80% complete
  • 6th to 7th floor putty 1st coat completed
  • 8th floor putty 1st coat 60% complete
  • 9th to 16th floor putty 1st coat completed
  • 16th and 15th floor A, B – 2nd coat putty completed
  • East side outside primer – completed
  • South side primer – completed
  • North side primer – completed
  • Painting inside Apartment – 1st coat emulsion commenced – In progress

March 2024

WORK STATUS – March 2024

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Sump tank plastering complete up to fireroom
  • GF to 17th floor column raising completed
  • 1st to 16th floor slab centering and shuttering completed
  • 1st to 16th floor slab concrete completed
  • Terrace roof slab column rising completed
  • Terrace roof slab concrete completed
  • Stair roof slab completed
  • Overhead tank completed

MASONRY WORKS

  • 2nd floor plastering 50% completed
  • 3rd to 16th floor apartment ceiling plastering completed
  • 3rd to 16th floor block masonry completed
  • Terrace parapet block masonry work completed
  • 3rd to 16th floor wall plastering completed

MASONRY WORKS – OUTSIDE PLASTERING

  • South Side – ABC Outside

South side external wall plastering from 3rd to 17th floor completed

  • East Side 

A, Fire Stair, F type Apartment from 3rd to 17th floor completed

  • North Side

D, E, F type Apartment from 3rd to 17th floor completed

  • West Side

C, D Type – 75% of the outside area completed

 

ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING

  • Electrical work 3rd to 16th floor – completed

PLUMBING WORKS

  • Plumbing work 3rd to 16th floor – completed.

WATERPROOFING WORKS

  • 3rd to 15th floor waterproofing completed
  • 16th floor waterproofing – 90% completed
  • Terrace floor – 80% completed

FIRE AND SAFETY WORK

  • 3rd to 16th floor fire and safety work completed

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor tile work completed
  • 16th floor – 50% complete
  • 15th floor – 80% complete
  • 14th floor – 75% complete
  • 13th floor – 65% complete
  • 12th floor – 60% complete
  • 11th floor – 70% complete
  • 10th floor – 30% complete

PAINTING WORK

  • Putty and painting work on 3F completed
  • 3rd to 4th floor putty 1st coat completed
  • 5th floor putty 1st coat 80% complete
  • 6th to 7th floor putty 1st coat completed
  • 8th floor putty 1st coat 50% complete
  • 9th to 15th floor putty 1st coat completed
  • 16th floor putty 1st coat 60% complete
  • 16th and 15th floor A, B – 2nd coat putty completed
  • East side outside primer – completed
  • South side primer – completed
  • North side primer – 50% completed
February 2024

WORK STATUS – February 2024

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 13th to 14th floor column raising completed
  • 14th floor slab concrete completed
  • 14th to 15th column raising completed
  • 15th floor slab concrete completed
  • 15th to 16th column raising completed
  • 16th floor slab concrete completed
  • Terrace roof slab column rising completed
  • Terrace roof slab concrete completed
  • Stair roof slab completed
  • Over head tank completed

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering completed
  • 11th floor apartment ceiling plastering completed
  • 12th floor apartment ceiling plastering completed
  • 13th floor apartment ceiling plastering completed
  • 14th floor apartment ceiling plastering completed
  • 15th floor apartment ceiling plastering completed
  • 16th floor apartment ceiling plastering complete
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 10th floor block masonry completed
  • 11th floor block masonry completed
  • 12th floor block masonry completed
  • 13th floor block masonry completed
  • 14th floor block masonry completed
  • 15th floor block masonry completed
  • 16th floor block masonry completed
  • Terrace parapet block masonry work completed
  • 3rd floor wall plastering completed
  • 4th floor wall plastering work completed
  • 5th floor wall plastering completed
  • 6th floor wall plastering completed
  • 7th floor wall plastering completed
  • 8th floor wall plastering completed
  • 9th floor wall plastering completed
  • 10th floor wall plastering completed
  • 11th floor wall plastering completed
  • 12th floor wall plastering completed
  • 13th floor wall plastering completed
  • 14th floor wall plastering completed
  • 15th floor wall plastering completed
  • 16th floor wall plastering completed

MASONRY WORKS – OUTSIDE PLASTERING

  • South Side – ABC Outside

South side external wall plastering from 3rd to 17th floor completed

  • East Side

A, Fire Stair, F type Apartment from 3rd to 17th floor completed

  • North Side

D, E, F Type – 50% of the outside area completed

  • West Side

C, D Type – 40% of the outside area completed

ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor-completed
  • Electrical work-5th floor –completed
  • Electrical work- 6th floor –completed
  • Electrical work- 7th floor – completed
  • Electrical work- 8th floor – complete
  • Electrical work- 9th floor – completed
  • Electrical work- 10th floor – completed
  • Electrical work- 11th floor – complete
  • Electrical work- 12th floor – completed
  • Electrical work- 13th floor –completed
  • Electrical work- 14th floor –completed
  • Electrical work- 15th floor –completed
  • Electrical work- 16th floor –completed

PLUMBING WORKS

  • Plumbing work 3th floor – completed.
  • Plumbing work 4th floor – completed
  • Plumbing work 5th floor – completed
  • Plumbing work 6th floor – completed
  • Plumbing work 7th floor – completed
  • Plumbing work 8th floor – completed
  • Plumbing work 9th floor – completed
  • Plumbing work 10th floor – completed
  • Plumbing work 11th floor – completed
  • Plumbing work 12th floor – completed
  • Plumbing work 13th floor – completed
  • Plumbing work 14th floor – completed
  • Plumbing work 15th floor – completed
  • Plumbing work 16th floor – completed

WATERPROOFING WORKS

  • 3rd floor waterproofing completed
  • 4th floor waterproofing completed
  • 5th floor waterproofing completed
  • 6th floor waterproofing completed
  • 7th floor waterproofing completed
  • 8th floor waterproofing completed
  • 9th floor waterproofing completed
  • 10th floor waterproofing completed
  • 11th floor waterproofing completed
  • 12th floor waterproofing completed
  • 13th floor waterproofing completed
  • 14th floor waterproofing completed
  • 15th floor waterproofing – 85% completed
  • 16th floor waterproofing – 90% completed

FIRE AND SAFETY WORK

  • 3rd floor fire and safety work completed
  • 4th floor fire and safety work completed
  • 5th floor fire and safety work completed
  • 6th floor fire and safety work completed
  • 7th floor fire and safety work completed
  • 8th floor fire and safety work completed
  • 9th floor fire and safety work completed
  • 10th floor fire and safety work completed
  • 11th floor fire and safety work completed
  • 12th floor fire and safety work completed
  • 13th floor fire and safety work completed
  • 14th floor fire and safety work completed
  • 15th floor fire and safety work completed
  • 16th floor fire and safety work completed

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor tile work completed
  • 16th floor – 40% complete
  • 15th floor toilet wall tile laying – 50% complete
  • 14th floor toilet tile – 50% complete
  • 13th floor toilet wall tile – 50% complete

PAINTING WORK

  • Putty and painting work on 3F completed
  • 3rd floor putty 1st coat completed
  • 4th floor putty 1st coat completed
  • 5th floor putty 1st coat 80% complete
  • 6th floor putty 1st coat completed
  • 7th floor putty 1st coat completed
  • 8th floor putty 1st coat 50% complete
  • 9th floor putty 1st coat completed
  • 10th floor putty 1st coat completed
  • 11th floor putty 1st coat completed
  • 12th floor putty 1st coat completed
  • 13th floor putty 1st coat completed
  • 14th floor putty 1st coat completed
  • 15th floor putty 1st coat completed
  • 16th floor putty 1st coat 60% complete
January 2024

WORK STATUS – January 2024

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 13th to 14th floor column raising completed
  • 14th floor slab concrete completed
  • 14th to 15th column raising completed
  • 15th floor slab concrete completed
  • 15th to 16th column raising completed
  • 16th floor slab concrete completed
  • Terrace roof slab column rising completed
  • Terrace roof slab concrete completed
  • Stair roof slab completed
  • Overhead tank completed

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering completed
  • 11th floor apartment ceiling plastering completed
  • 12th floor apartment ceiling plastering completed
  • 13th floor apartment ceiling plastering completed
  • 14th floor apartment ceiling plastering completed
  • 15th floor apartment ceiling plastering completed
  • 16th floor apartment ceiling plastering complete
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 10th floor block masonry completed
  • 11th floor block masonry completed
  • 12th floor block masonry completed
  • 13th floor block masonry completed
  • 14th floor block masonry completed
  • 15th floor block masonry completed
  • 16th floor block masonry completed
  • Terrace parapet block masonry work completed
  • 3rd floor wall plastering completed
  • 4th floor wall plastering work completed
  • 5th floor wall plastering completed
  • 6th floor wall plastering completed
  • 7th floor wall plastering completed
  • 8th floor wall plastering completed
  • 9th floor wall plastering completed
  • 10th floor wall plastering completed
  • 11th floor wall plastering completed
  • 12th floor wall plastering completed
  • 13th floor wall plastering completed
  • 14th floor wall plastering completed
  • 15th floor wall plastering completed
  • 16th floor wall plastering completed

MASONRY WORKS – OUTSIDE PLASTERING

  • South Side – ABC Outside

South side external wall plastering from 3rd to 17th floor completed

  • East Side

A, Fire Stair, F type Apartment from 3rd to 17th floor completed

  • North Side

D, E, F Type – 30% of the outside area completed

 ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor-completed
  • Electrical work-5th floor –completed
  • Electrical work- 6th floor –completed
  • Electrical work- 7th floor – completed
  • Electrical work- 8th floor – complete
  • Electrical work- 9th floor – completed
  • Electrical work- 10th floor – completed
  • Electrical work- 11th floor – complete
  • Electrical work- 12th floor – completed
  • Electrical work- 13th floor –completed
  • Electrical work- 14th floor –completed
  • Electrical work- 15th floor –completed
  • Electrical work- 16th floor –completed

PLUMBING WORKS – PIPELINE WORKS & PRESSURE TESTING WORKS

  • Plumbing work 3th floor – completed.
  • Plumbing work 4th floor – completed
  • Plumbing work 5th floor – completed
  • Plumbing work 6th floor – completed
  • Plumbing work 7th floor – completed
  • Plumbing work 8th floor – completed
  • Plumbing work 9th floor – completed
  • Plumbing work 10th floor – completed
  • Plumbing work 11th floor – completed
  • Plumbing work 12th floor – completed
  • Plumbing work 13th floor – completed
  • Plumbing work 14th floor – completed
  • Plumbing work 15th floor – completed
  • Plumbing work 16th floor – 50% complete

WATERPROOFING WORKS

  • 3rd floor waterproofing completed
  • 4th floor waterproofing completed
  • 5th floor waterproofing completed
  • 6th floor waterproofing completed
  • 7th floor waterproofing completed
  • 8th floor waterproofing completed
  • 9th floor waterproofing completed
  • 10th floor waterproofing completed
  • 11th floor waterproofing completed
  • 12th floor waterproofing completed
  • 13th floor waterproofing completed
  • 14th floor waterproofing – 85% completed
  • 15th floor waterproofing – 85% completed
  • 16th floor waterproofing – 85% completed

FIRE AND SAFETY WORK

  • 3rd floor fire and safety work completed
  • 4th floor fire and safety work completed
  • 5th floor fire and safety work completed
  • 6th floor fire and safety work completed
  • 7th floor fire and safety work completed
  • 8th floor fire and safety work completed
  • 9th floor fire and safety work completed
  • 10th floor fire and safety work completed
  • 11th floor fire and safety work completed
  • 12th floor fire and safety work completed
  • 13th floor fire and safety work completed
  • 14th floor fire and safety work 75% complete
  • 15th floor fire and safety work 75% complete
  • 16th floor fire and safety work 75% complete

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor tile work completed
  • 16th floor – 35% complete

PAINTING WORK

  • Putty and painting work on 3F completed
  • 3rd floor putty 1st coat completed
  • 4th floor putty 1st coat completed
  • 5th floor putty 1st coat 80% complete
  • 6th floor putty 1st coat completed
  • 7th floor putty 1st coat completed
  • 8th floor putty 1st coat 50% complete
  • 9th floor putty 1st coat completed
  • 10th floor putty 1st coat completed
  • 11th floor putty 1st coat completed
  • 12th floor putty 1st coat completed
  • 13th floor putty 1st coat completed
  • 14th floor putty 1st coat completed
  • 15th floor putty 1st coat completed
  • 16th floor putty 1st coat 50% complete
December 2023
  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 13th to 14th floor column raising completed
  • 14th floor slab concrete completed
  • 14th to 15th column raising completed
  • 15th floor slab concrete completed
  • 15th to 16th column raising completed
  • 16th floor slab concrete completed
  • Terrace roof slab column rising completed
  • Terrace roof slab concrete completed
  • Stair roof slab completed
  • Overhead tank completed

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering completed
  • 11th floor apartment ceiling plastering completed
  • 12th floor apartment ceiling plastering completed
  • 13th floor apartment ceiling plastering completed
  • 14th floor apartment ceiling plastering completed
  • 15th floor apartment ceiling plastering completed
  • 16th floor apartment ceiling plastering complete
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 10th floor block masonry completed
  • 11th floor block masonry completed
  • 12th floor block masonry completed
  • 13th floor block masonry completed
  • 14th floor block masonry completed
  • 15th floor block masonry completed
  • 16th floor block masonry completed
  • Terrace parapet block masonry work completed
  • 3rd floor wall plastering completed
  • 4th floor wall plastering work completed
  • 5th floor wall plastering completed
  • 6th floor wall plastering completed
  • 7th floor wall plastering completed
  • 8th floor wall plastering completed
  • 9th floor wall plastering completed
  • 10th floor wall plastering completed
  • 11th floor wall plastering completed
  • 12th floor wall plastering completed
  • 13th floor wall plastering completed
  • 14th floor wall plastering completed
  • 15th floor wall plastering completed
  • 16th floor wall plastering completed

ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor-completed
  • Electrical work-5th floor –completed
  • Electrical work- 6th floor –completed
  • Electrical work- 7th floor – completed
  • Electrical work- 8th floor – 75% complete
  • Electrical work- 9th floor – complete
  • Electrical work- 10th floor – completed
  • Electrical work- 11th floor – complete
  • Electrical work- 12th floor – completed
  • Electrical work- 13th floor –completed
  • Electrical work- 14th floor –completed
  • Electrical work- 15th floor –completed
  • Electrical work- 16th floor –50% complete

PLUMBING WORKS

  • Plumbing work 3rd floor – completed.
  • Plumbing work 4th floor – completed
  • Plumbing work 5th floor – completed
  • Plumbing work 6th floor – completed
  • Plumbing work 7th floor – completed
  • Plumbing work 8th floor – 95%completed
  • Plumbing work 9th floor – 85%completed
  • Plumbing work 10th floor – completed
  • Plumbing work 11th floor – completed
  • 3rd to 16th floor core cutting and sleeve fix completed

WATERPROOFING WORKS

  • 3rd floor waterproofing completed
  • 4th floor waterproofing completed
  • 5th floor waterproofing completed
  • 6th floor waterproofing completed
  • 7th floor waterproofing completed
  • 8th floor waterproofing completed
  • 9th floor waterproofing completed
  • 10th floor waterproofing completed
  • 11th floor waterproofing completed
  • 12th floor waterproofing completed
  • 13th floor waterproofing – 50% completed

FIRE AND SAFETY WORK

  • 3rd floor fire and safety work completed
  • 4th floor fire and safety work completed
  • 5th floor fire and safety work completed
  • 6th floor fire and safety work completed
  • 7th floor fire and safety work completed
  • 8th floor fire and safety work completed
  • 9th floor fire and safety work completed
  • 10th floor fire and safety work completed
  • 11th floor fire and safety work completed
  • 12th floor fire and safety work completed
  • 13th floor fire and safety work – 85% completed

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor tile work completed

PAINTING WORK

  • Putty and painting work on 3F completed
  • 3rd floor putty 1st coat completed
  • 4th floor putty 1st coat completed
  • 5th floor putty 1st coat 80% complete
  • 6th floor putty 1st coat completed
  • 7th floor putty 1st coat completed
  • 8th floor putty 1st coat 50% complete
  • 9th floor putty 1st coat 80% complete
  • 10th floor putty 1st coat completed
  • 11th floor putty 1st coat completed
  • 12th floor putty 1st coat completed
  • 13th floor putty 1st coat completed
  • 14th floor putty 1st coat completed
  • 15th floor putty work in progress – 20%
November 2023

WORK STATUS – November 2023

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 13th to 14th floor column raising completed
  • 14th floor slab concrete completed
  • 14th to 15th column raising completed
  • 15th floor slab concrete completed
  • 15th to 16th column raising completed
  • 16th floor slab concrete completed
  • Terrace roof slab column rising completed
  • Terrace roof slab concrete completed
  • Stair roof slab completed
  • OHT work completed

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering completed
  • 11th floor apartment ceiling plastering completed
  • 12th floor apartment ceiling plastering completed
  • 13th floor apartment ceiling plastering completed
  • 14th floor apartment ceiling plastering completed
  • 15th floor apartment ceiling plastering completed
  • 16th floor apartment ceiling plastering complete
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 10th floor block masonry completed
  • 11th floor block masonry completed
  • 12th floor block masonry completed
  • 13th floor block masonry completed
  • 14th floor block masonry completed
  • 15th floor block masonry completed
  • 16th floor block masonry completed
  • Terrace parapet block masonry work completed
  • 3rd floor wall plastering completed
  • 4th floor wall plastering work completed
  • 5th floor wall plastering completed
  • 6th floor wall plastering completed
  • 7th floor wall plastering completed
  • 8th floor wall plastering completed
  • 9th floor wall plastering completed
  • 10th floor wall plastering completed
  • 11th floor wall plastering completed
  • 12th floor wall plastering completed
  • 13th floor wall plastering completed
  • 14th floor wall plastering completed
  • 15th floor wall plastering completed
  • 16th floor wall plastering work progressing – 50%

ELECTRICAL WORKS

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor-completed
  • Electrical work-5th floor –completed
  • Electrical work- 6th floor –completed
  • Electrical work- 7th floor – completed
  • Electrical work- 8th floor – 50% complete
  • Electrical work- 9th floor – 90% complete
  • Electrical work- 10th floor – completed
  • Electrical work- 11th floor – 90% complete
  • Electrical work- 12th floor – completed
  • Electrical work- 13th floor –completed
  • Electrical work- 14th floor –completed
  • Electrical work- 15th floor –completed
  • Electrical work- 16th floor –50% complete

PLUMBING WORKS

  • Plumbing work 3rd floor – completed.
  • Plumbing work 4th floor – completed
  • Plumbing work 5th floor –completed
  • Plumbing work 6th floor –completed
  • Plumbing work 7th floor –50% completed
  • Plumbing work 8th floor – 95% completed
  • Plumbing work 9th floor – 85% completed
  • 3 to 12th floor core cutting and sleeve fix completed

WATERPROOFING WORKS

  • 3rd floor waterproofing completed
  • 4th floor waterproofing completed
  • 5th floor waterproofing completed
  • 6th floor waterproofing completed
  • 7th floor waterproofing completed
  • 8th floor waterproofing completed
  • 9th floor waterproofing completed
  • 10th floor waterproofing completed
  • 11th floor waterproofing – 70% completed

FIRE AND SAFETY WORK

  • 3rd floor fire and safety work completed
  • 4th floor fire and safety work completed
  • 5th floor fire and safety work completed
  • 6th floor fire and safety work completed
  • 7th floor fire and safety work completed
  • 8th floor fire and safety work completed
  • 9th floor fire and safety work completed
  • 10th floor fire and safety work completed
  • 11th floor fire and safety work completed

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor

PAINTING WORK

  • Putty and painting work on 3F under progress
  • 3rd floor putty 1st coat completed
  • 4th floor putty 1st coat completed
  • 5th floor putty 1st coat 80% complete
  • 6th floor putty 1st coat completed
  • 7th floor putty 1st coat completed
  • 8th floor putty 1st coat 50% complete
  • 9th floor putty 1st coat 80% complete
  • 10th floor putty 1st coat completed

 

October 2023

WORK STATUS – October 2023

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 13th to 14th floor column raising completed
  • 14th floor slab concrete completed
  • 14th to 15th column raising completed
  • 15th floor slab concrete completed
  • 15th to 16th column raising completed
  • 16th floor slab concrete completed
  • Terrace roof slab column rising completed
  • Terrace roof slab concrete completed
  • Stair roof slab completed
  • OHT work under progress

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering completed
  • 11th floor apartment ceiling plastering completed
  • 12th floor apartment ceiling plastering completed
  • 13th floor apartment ceiling plastering completed
  • 14th floor apartment ceiling plastering completed
  • 15th floor apartment ceiling plastering completed
  • 16th floor apartment ceiling plastering in progress -50%
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 10th floor block masonry completed
  • 11th floor block masonry completed
  • 12th floor block masonry completed
  • 13th floor block masonry completed
  • 14th floor block masonry completed
  • 15th floor block masonry completed
  • 16th floor block masonry work progressing -50%
  • Terrace parapet block masonry work progressing – 20%
  • 3rd floor wall plastering completed
  • 4th floor wall plastering work completed
  • 5th floor wall plastering completed
  • 6th floor wall plastering completed
  • 7th floor wall plastering completed
  • 8th floor wall plastering completed
  • 9th floor wall plastering completed
  • 10th floor wall plastering completed
  • 11th floor wall plastering completed
  • 12th floor wall plastering completed
  • 13th floor wall plastering work progressing – 50%
  • 14th floor wall plastering work progressing – 25%

ELECTRICAL WORKS

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor-completed
  • Electrical work-5th floor –completed
  • Electrical work- 6th floor –completed
  • Electrical work- 7th floor – completed
  • Electrical work- 8th floor – completed
  • Electrical work- 9th floor – completed
  • Electrical work- 10th floor – completed
  • Electrical work- 11th floor – completed
  • Electrical work- 12th floor – completed
  • Electrical work- 13th floor – 50% completed
  • Electrical work- 14th floor – 25% completed

PLUMBING WORKS

  • Plumbing work 3th floor – completed.
  • Plumbing work 4th floor – completed
  • Plumbing work 5th floor – 30% complete
  • Plumbing work 5th floor – 20% complete
  • 3 to 9th floor core cutting and sleeve fix completed

WATERPROOFING WORKS

  • 3rd floor waterproofing completed
  • 4th floor waterproofing completed
  • 5th floor waterproofing completed
  • 6th floor waterproofing completed
  • 7th floor waterproofing completed
  • 8th floor waterproofing completed
  • 9th floor waterproofing completed
  • 10th floor waterproofing completed
  • 11th floor waterproofing – 50% completed

FIRE AND SAFETY WORK

  • 3rd floor fire and safety work completed
  • 4th floor fire and safety work completed
  • 5th floor fire and safety work in progress -25%
  • 6th floor fire and safety work completed
  • 7th floor fire and safety work completed

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor under progress

PAINTING WORK

  • Putty and painting work on 3F under progress
September 2023

WORK STATUS – September 2023

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 14th floor part 1st slab concrete completed
  • 14th floor part 2nd shuttering work completed
  • 14th to 15th column raising completed
  • 15th floor slab concrete completed
  • 16th floor slab concrete completed
  • Cover slab column rising completed
  • Stair roof slab in progress

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering completed
  • 11th floor ceiling plastering completed
  • 12th floor ceiling plastering completed
  • 13th floor ceiling plastering completed
  • 14th floor ceiling plastering completed
  • 15th floor ceiling plastering in progress -50%
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 10th floor block masonry completed
  • 11th floor block masonry completed
  • 12th floor block masonry completed
  • 13th floor block masonry completed
  • 14th floor block masonry completed
  • 15th floor block masonry work progressing -50%
  • 3rd floor wall plastering completed
  • 4th floor wall plastering work completed
  • 5th floor wall plastering completed
  • 6th floor wall plastering completed
  • 7th floor wall plastering completed
  • 8th floor wall plastering completed
  • 9th floor wall plastering completed
  • 10th floor wall plastering completed
  • 11th floor wall plastering completed
  • 12th floor wall plastering in progress -10%

ELECTRICAL WORKS

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor-completed
  • Electrical work-5th floor –completed
  • Electrical work- 6th floor –completed
  • Electrical work- 7th floor – completed
  • Electrical work- 8th floor – completed
  • Electrical work- 9th floor – completed
  • Electrical work- 10th floor – completed
  • Electrical work- 11th floor – completed
  • Electrical work- 12th floor – completed
  • Electrical work- 13th floor – 50% completed

PLUMBING WORKS

  • Plumbing work 3th floor – completed.
  • Plumbing work 4th floor – completed
  • Plumbing work 5th floor – completed
  • 3 to 9th floor core cutting and sleeve fix completed

WATERPROOFING WORKS

  • 3rd floor waterproofing completed
  • 4th floor waterproofing completed
  • 5th floor waterproofing completed
  • 6th floor waterproofing completed
  • 7th floor waterproofing completed
  • Waterproofing 8th floor – 50%

FIRE AND SAFETY WORK

  • 3rd floor fire and safety work completed
  • 4th floor fire and safety work in progress -50%
  • 5th floor fire and safety work in progress -25%
  • 6th floor fire and safety work completed

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor tile work completed
Magnolia August 2023
  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 14th floor part 1st slab concrete completed
  • 14th floor part 2nd shuttering work completed
  • 14th to 15th column raising completed
  • 15th floor slab concrete completed
  • 16th floor slab concrete completed
  • Terrace floor slab concrete is progress

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering completed
  • 11th floor ceiling plastering completed
  • 12th floor ceiling plastering completed
  • 13th floor ceiling plastering completed
  • 14th floor ceiling plastering completed
  • 15th floor ceiling plastering is progress
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 10th floor block masonry completed
  • 11th floor block masonry completed
  • 12th floor block masonry completed
  • 13th floor block masonry completed
  • 14th floor block masonry is progress – 50%
  • 3rd floor wall plastering completed
  • 4th floor wall plastering work completed
  • 5th floor wall plastering completed
  • 6th floor wall plastering completed
  • 7th floor wall plastering completed
  • 8th floor wall plastering in completed
  • 9th floor wall plastering in completed
  • 10th floor wall plastering in progress – 90%
  • 11th floor wall plastering in progress – 10%

ELECTRICAL WORKS

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor-completed
  • Electrical work-5th floor –completed
  • Electrical work- 6th floor –completed
  • Electrical work- 7th floor – completed
  • Electrical work- 8th floor – completed
  • Electrical work- 9th floor – completed
  • Electrical work- 10th floor – completed
  • Electrical work- 11th floor – completed
  • Electrical work- 12th floor – 50% completed

PLUMBING WORKS

  • Plumbing work 3th floor – completed.
  • Plumbing work 4th floor – completed
  • Plumbing work 5th floor – completed
  • 3 to 6th floor core cutting and sleeve fix completed

WATERPROOFING WORKS

  • Waterproofing 3th floor Toilet – completed.
  • Waterproofing 4th floor – 50%
July 2023
  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 14th floor part 1st slab concrete completed
  • 14th floor part 2nd shuttering work completed
  • 14th to 15th column raising completed
  • 15th floor slab concrete completed
  • 16th floor slab concrete completed
  • Terrace floor slab column rising in progress

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering completed
  • 11th floor ceiling plastering completed
  • 12th floor ceiling plastering completed
  • 13th floor ceiling plastering in progress -80%
  • 14th floor ceiling plastering in progress -30%
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 10th floor block masonry completed
  • 11th floor block masonry completed
  • 12th floor block masonry work progressing -80%
  • 13th floor block masonry work progressing – 30%
  • 3rd floor wall plastering completed
  • 4th floor wall plastering work completed
  • 5th floor wall plastering completed
  • 6th floor wall plastering completed
  • 7th floor wall plastering completed
  • 8th floor wall plastering in progress – 50%
  • 9th floor wall plastering in progress -10%

ELECTRICAL WORKS

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor – completed
  • Electrical work-5th floor –completed
  • Electrical work- 6th floor –completed
  • Electrical work- 7th floor – completed
  • Electrical work- 8th floor – completed
  • Electrical work- 9th floor – completed
  • Electrical work- 10th floor – completed
  • Electrical work- 11th floor – 50% completed

PLUMBING WORKS

  • Plumbing work 3F Apartment wall chasing and pipe laying completed.
  • Plumbing work 3A,3B,3C,3D&3E apartment in progress 80%
  • Plumbing work 4th Floor in progress 25%
May 2023
  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th  column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th  floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 14th floor part 1st slab concrete completed
  • 14th floor part 2nd shuttering work completed
  • 14th to 15th part 1st column reinforcement completed

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering -60% completed
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 3rd floor wall plastering completed
  • 4 A and 4 B wall plastering work in progress – 50% completed

ELECTRICAL WORKS

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor-completed
  • Electrical work-5th floor –box fixing work in progress

PLUMBING WORKS

  • Plumbing work 3F Apartment wall chasing and pipe laying completed.
  • Plumbing work 3A,3B,3C,3D&3E apartment in progress 20%
April 2023
  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th  column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th  floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor part 1 slab concrete completed
  • 13th floor part 11 shuttering work in progress – 75% completed

MASONRY  WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment 9A,9B,9C ceiling plastering -45% completed
  • 3rd floor block work setting out completed
  • 4th floor block work setting out completed
  • 5th floor block work setting out completed
  • 6th floor block work setting out completed
  • 7th floor block work setting out completed
  • 8th floor 8A, 8B block work setting out completed
  • 8C block work setting out -work in progress
  • 3rd floor sample apartment 3E,3F wall plastering completed
  • 3A and 3B wall plastering work in progress – 50% completed

ELECTRICAL  WORKS

  • Electrical work 3rd floor – wall chasing, conduit and metal box fixing completed
  • Electrical work 4th floor work in progress

PLUMBING  WORKS

  • Plumbing work 3F Apartment wall chasing and pipe laying completed.
  • Plumbing work 3A,3B,3C,3D&3E apartment in progress 20%
March 2023

WORK STATUS – MARCH  2023

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th  column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th  floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor part 1 slab concrete completed
  • 11th to 12th column raising part 1 – 20% completed
  • 11th floor part II shuttering work in progress – 85% completed

MASONRY  WORKS

  • 3rd floor 3F Sample apartment masonry work completed
  • 3rd floor 3D apartment masonry work completed
  • 3rd floor 3E apartment masonry work  completed
  • 3rd floor 3A,3B,3C apartment masonry work completed
  • 4th floor 4A,4B,4D,4E,4F apartment masonry work completed
  • 5th floor 5B,5C apartment masonry work – 40% completed
  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment – ceiling plastering – 40% completed
  • 3rd floor block work setting out completed
  • 4th floor block work setting out completed
  • 5th floor block work setting out – 5A,5B,5C – completed
  • 5th floor block work setting out – 5D – 60 % completed

ELECTRICAL  WORKS

  • Electrical work 3F Apartment- wall chasing, conduit and metal box fixing completed
  • Electrical work 3A,3B,3C,3D &3E in progess 25%

PLUMBING  WORKS

  • Plumbing work 3F Apartment wall chasing and pipe laying completed.
  • Plumbing work 3A,3B,3C,3D&3E apartment in progress 20%
February 2023
  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th foor slab concrete completed
  • 7th to 8th floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor part 1 ‐ slab centering and shuttering completed
  • 10th floor part 1 slab concrete completed

 MASONRY WORKS

  • 3rd floor 3F Sample apartment masonry work completed
  • 3rd floor 3D apartment masonry work completed
  • 3rd floor 3E apartment masonry work completed
  • 3rd floor 3A,3B,3C apartment masonry work completed
  • 4th floor 4D apartment masonry work completed
  • 4th floor 4E apartment masonry work ‐ 60 % completed
  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ‐6A,6B ceiling plastering completed
  • 6th floor apartment ‐6C ceiling plastering ‐ 50% completed
  • 3rd floor block work setting out completed
  • 4th floor block work setting out completed
  • 5th floor block work setting out ‐ 5A,5B,5C ‐ completed
  • 5th floor block work setting out ‐ 5D ‐ 50 % completed

 ELECTRICAL WORKS

  • Electrical work 3F Apartment‐ wall chasing, conduit and metal box fixing completed

 PLUMBING WORKS

  • Plumbing work 3F Apartment wall chasing and pipe laying completed.
January 2023
  • 9th floor slab shuttering and centering work in progress – 50% completed
  • 8th to 9th floor column raising -75% completed
  • 8th floor slab concrete – completed
  • Masonry work in progress – ceiling plastering & block work – 40%
  • 7th Floor slab concrete completed
  • Sixth floor slab concrete completed
  • Fifth floor slab concrete completed
  • Fourth floor slab concrete completed
  • Third floor slab concrete completed
  • Second floor slab concrete completed
  • First floor slab concrete completed
  • Column raising first floor completed
  • All pile foundation works completed
  • Sump tank works completed
  • Column raising ground floor completed
  • Earth filling completed
December 2022
  • 8th floor slab concrete – 50% completed
  • Masonry work in progress – 25% completed (plastering & block work)
  • 7th Floor slab concrete completed – centering and shuttering
  • Sixth floor slab concrete completed
  • Column raising concrete in progress 50%
  • Fifth floor slab concrete completed
  • Fourth floor slab concrete completed
  • Third floor slab 100% completed
  • Second floor slab completed
  • Column raising second floor 100% completed
  • First floor slab completed
  • Column raising first floor completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • Earth filling completed
  • Column raising concrete in progress 50%
November 2022
  • 7th Floor slab in progress 35% completed – centering and shuttering
  • Sixth floor slab concrete completed
  • Column raising concrete in progress 50
  • Fifth floor slab concrete completed
  • Fourth floor slab concrete completed
  • Third floor slab 100% completed
  • Second floor slab completed
  • Column raising second floor 100% completed
  • First floor slab completed
  • Column raising first floor completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • Earth filling completed
October 2022
  • Sixth floor slab centering and shuttering in progress 40%
  • Column raising concrete in progress 50
  • Fifth floor slab concrete completed
  • Fourth floor slab concrete completed
  • Third floor slab 100% completed
  • Second floor slab completed
  • Column raising second floor 100% completed
  • First floor slab completed
  • Column raising first floor completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • Earth filling completed
September 2022
  • Fifth floor slab centering and shuttering in progress 60 percentage completed
  • Fourth floor slab concrete completed
  • Third floor slab 100% completed
  • Second floor slab completed
  • First floor slab completed
  • 4 All pile foundation work completed
  • Sump tank work completed
  • Earth filling completed
  • Column raising ground floor completed
  • Column raising first floor completed
  • Column raising second floor 100% completed
Work status as of 18th August 2022
  1. Fourth floor slab shuttering and centering works in progress 50% complete.
  2. Earth filling completed
  3. All pile foundation work completed
  4. Sump tank work completed
  5. Column raising ground floor completed
  6. First floor slab completed
  7. Column raising first floor completed
  8. Second floor slab completed
  9. Column raising second floor 100% completed
  10. Third floor slab 100% completed
Work as of 7th July 2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. Column raising ground floor completed
  5. First floor slab completed
  6. Column raising first floor completed
  7. Second floor slab completed
  8. Column raising second floor 100% completed
  9. Third floor slab 50% completed
Work as of 7th June 2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. Column raising ground floor completed
  5. First floor slab completed
  6. Column raising first floor completed
  7. Second floor slab 70% completed

8.column raising second floor 25% completed

Work as of 9th May 2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. First floor slab 100% concrete completed
  5. Column raising ground floor 100% completed
  6. Column raising first floor 100% completed
  7. Second floor slab 25% completed
Work as of 21st April 2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. First floor slab 100% concrete completed
  5. Column raising ground floor 100% completed
  6. Column raising first floor 60% completed
Work as of 8th March 2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. First floor slab 30% concrete completed
  5. First floor slab second half area shuttering work started
  6. Column raising ground floor 95% completed
Work as of 25th Feb.2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. Main stair first landing concrete done
  5. First floor slab half portion shuttering completed
  6. Steel work for first floor slab started
  7. Ground floor lift wall raised
  8. Column raising 95% completed
Work as of 28th Jan.2022
  1. Earth filling completed
  2. Piling works 100% completed
  3. Pile caps 65% completed
  4. Ground floor column raising work 80% completed
  5. Sump tank completed
  6. Ground floor lift pit completed
  7. Ground floor stair well shuttering started
  8. Compaction of ground floor 60% completed
  9. First floor slab shuttering work started
  10. Grade beam 60% completed
  11. Work slow down due to omicron
Work as of 32st Dec.2021
  1. Earth filling completed
  2. Piling works 100% completed
  3. Sump tank work 100% completed
  4. Lift wall shuttering upto ff.lvl completed
  5. Ground floor columns raising 30% completed
Work as of 3rd Nov.2021
  1. Earth filling completed
  2. Piling works 100% completed
  3. Grade beams work 10% completed
  4. Sump tank work 50% completed
  5. Pile cap concreting work in progress 50% completed
  6. Ground floor columns raising 15% completed
Work as of 20th Oct.2021
  1. Earth filling completed
  2. Piling works 100% completed
  3. Pile cap concreting work in progress 25% completed
Work as of 19th Sept.2021
  1. Earth filling completed
  2. Piling works 100% completed
  3. Pile cap earthwork started
  4. Pile chipping work started
  5. Pile cap shuttering and steel works started
Work as of 12th Aug.2021
  1. Earth filling completed
  2. Piling works 80% completed
  3. Work not in full swing due to covid -19 pandamic
Work as of 28th July 2021
  1. Earth filling completed
  2. Piling 40% completed
  3. Work not in full swing due to covid -19 pandamic
Work as of 13.04.21 to 20.06.21

Lockdown and containment zone restrictions
No work done

Work as of 5th April. 2021
  1. Earth filling completed
  2. Pile load test
  3. Work not in full swing due to covid -19 pandamic
Work as of 8th March. 2021
  1. Borewell completed
  2. Earth filling completed
  3. Test pile work conducted
  4. Work not in full swing due to covid -19 pandamic
Work as of 12th Feb. 2021
  1. Bhoomi pooja
  2. Site office work completed
  3. Cement shed work completed
  4. Work not in full swing due to covid -19 pandamic
Work as of 9th Jan. 2021
  1. Site clearance
  2. Soil test
  3. Earth filling started
  4. Work not in full swing due to Covid -19 pandemic