Work Status
March 2023
WORK STATUS – MARCH 2023
- Earth filling completed
- All pile foundation work completed
- Sump tank work completed
- Column raising ground floor completed
- First floor slab completed
- Column raising first floor completed
- Second floor slab completed
- Column raising second floor completed
- Third floor slab completed
- Column raising third floor completed
- Fourth floor slab completed
- Column raising fourth floor completed
- Fifth floor slab completed
- Column raising sixth slab completed
- Third floor apartment type F, E and D ceiling plastering completed
- Sump tank plastering complete up to fireroom
- 6th floor slab centering and shuttering completed
- 6th floor slab concrete completed
- 6th to 7th column raising completed
- 7th floor slab centering and shuttering completed
- 7th floor slab concrete completed
- 7th to 8th floor column raising completed
- 8th floor slab centering and shuttering completed
- 8th floor slab concrete completed
- 8th to 9th floor column raising completed
- 9th floor slab centering and shuttering completed
- 9th floor slab concrete completed
- 9th to 10th floor column raising completed
- 10th floor slab concrete completed
- 10th to 11th floor column raising completed
- 11th floor part 1 slab concrete completed
- 11th to 12th column raising part 1 – 20% completed
- 11th floor part II shuttering work in progress – 85% completed
MASONRY WORKS
- 3rd floor 3F Sample apartment masonry work completed
- 3rd floor 3D apartment masonry work completed
- 3rd floor 3E apartment masonry work completed
- 3rd floor 3A,3B,3C apartment masonry work completed
- 4th floor 4A,4B,4D,4E,4F apartment masonry work completed
- 5th floor 5B,5C apartment masonry work – 40% completed
- 3rd floor apartment ceiling plastering completed
- 4th floor apartment ceiling plastering completed
- 5th floor apartment ceiling plastering completed
- 6th floor apartment ceiling plastering completed
- 7th floor apartment – ceiling plastering – 40% completed
- 3rd floor block work setting out completed
- 4th floor block work setting out completed
- 5th floor block work setting out – 5A,5B,5C – completed
- 5th floor block work setting out – 5D – 60 % completed
ELECTRICAL WORKS
- Electrical work 3F Apartment- wall chasing, conduit and metal box fixing completed
- Electrical work 3A,3B,3C,3D &3E in progess 25%
PLUMBING WORKS
- Plumbing work 3F Apartment wall chasing and pipe laying completed.
- Plumbing work 3A,3B,3C,3D&3E apartment in progress 20%
February 2023
- Earth filling completed
- All pile foundation work completed
- Sump tank work completed
- Column raising ground floor completed
- First floor slab completed
- Column raising first floor completed
- Second floor slab completed
- Column raising second floor completed
- Third floor slab completed
- Column raising third floor completed
- Fourth floor slab completed
- Column raising fourth floor completed
- Fifth floor slab completed
- Column raising sixth slab completed
- Third floor apartment type F, E and D ceiling plastering completed
- Sump tank plastering complete up to fireroom
- 6th floor slab centering and shuttering completed
- 6th floor slab concrete completed
- 6th to 7th column raising completed
- 7th floor slab centering and shuttering completed
- 7th foor slab concrete completed
- 7th to 8th floor column raising completed
- 8th floor slab centering and shuttering completed
- 8th floor slab concrete completed
- 8th to 9th floor column raising completed
- 9th floor slab centering and shuttering completed
- 9th floor slab concrete completed
- 9th to 10th floor column raising completed
- 10th floor part 1 ‐ slab centering and shuttering completed
- 10th floor part 1 slab concrete completed
MASONRY WORKS
- 3rd floor 3F Sample apartment masonry work completed
- 3rd floor 3D apartment masonry work completed
- 3rd floor 3E apartment masonry work completed
- 3rd floor 3A,3B,3C apartment masonry work completed
- 4th floor 4D apartment masonry work completed
- 4th floor 4E apartment masonry work ‐ 60 % completed
- 3rd floor apartment ceiling plastering completed
- 4th floor apartment ceiling plastering completed
- 5th floor apartment ceiling plastering completed
- 6th floor apartment ‐6A,6B ceiling plastering completed
- 6th floor apartment ‐6C ceiling plastering ‐ 50% completed
- 3rd floor block work setting out completed
- 4th floor block work setting out completed
- 5th floor block work setting out ‐ 5A,5B,5C ‐ completed
- 5th floor block work setting out ‐ 5D ‐ 50 % completed
ELECTRICAL WORKS
- Electrical work 3F Apartment‐ wall chasing, conduit and metal box fixing completed
PLUMBING WORKS
- Plumbing work 3F Apartment wall chasing and pipe laying completed.
January 2023
- 9th floor slab shuttering and centering work in progress – 50% completed
- 8th to 9th floor column raising -75% completed
- 8th floor slab concrete – completed
- Masonry work in progress – ceiling plastering & block work – 40%
- 7th Floor slab concrete completed
- Sixth floor slab concrete completed
- Fifth floor slab concrete completed
- Fourth floor slab concrete completed
- Third floor slab concrete completed
- Second floor slab concrete completed
- First floor slab concrete completed
- Column raising first floor completed
- All pile foundation works completed
- Sump tank works completed
- Column raising ground floor completed
- Earth filling completed
December 2022
- 8th floor slab concrete – 50% completed
- Masonry work in progress – 25% completed (plastering & block work)
- 7th Floor slab concrete completed – centering and shuttering
- Sixth floor slab concrete completed
- Column raising concrete in progress 50%
- Fifth floor slab concrete completed
- Fourth floor slab concrete completed
- Third floor slab 100% completed
- Second floor slab completed
- Column raising second floor 100% completed
- First floor slab completed
- Column raising first floor completed
- All pile foundation work completed
- Sump tank work completed
- Column raising ground floor completed
- Earth filling completed
- Column raising concrete in progress 50%
November 2022
- 7th Floor slab in progress 35% completed – centering and shuttering
- Sixth floor slab concrete completed
- Column raising concrete in progress 50
- Fifth floor slab concrete completed
- Fourth floor slab concrete completed
- Third floor slab 100% completed
- Second floor slab completed
- Column raising second floor 100% completed
- First floor slab completed
- Column raising first floor completed
- All pile foundation work completed
- Sump tank work completed
- Column raising ground floor completed
- Earth filling completed
October 2022
- Sixth floor slab centering and shuttering in progress 40%
- Column raising concrete in progress 50
- Fifth floor slab concrete completed
- Fourth floor slab concrete completed
- Third floor slab 100% completed
- Second floor slab completed
- Column raising second floor 100% completed
- First floor slab completed
- Column raising first floor completed
- All pile foundation work completed
- Sump tank work completed
- Column raising ground floor completed
- Earth filling completed
September 2022
- Fifth floor slab centering and shuttering in progress 60 percentage completed
- Fourth floor slab concrete completed
- Third floor slab 100% completed
- Second floor slab completed
- First floor slab completed
- 4 All pile foundation work completed
- Sump tank work completed
- Earth filling completed
- Column raising ground floor completed
- Column raising first floor completed
- Column raising second floor 100% completed
Work status as of 18th August 2022
- Fourth floor slab shuttering and centering works in progress 50% complete.
- Earth filling completed
- All pile foundation work completed
- Sump tank work completed
- Column raising ground floor completed
- First floor slab completed
- Column raising first floor completed
- Second floor slab completed
- Column raising second floor 100% completed
- Third floor slab 100% completed
Work as of 7th July 2022
- Earth filling completed
- All pile foundation work completed
- Sump tank work completed
- Column raising ground floor completed
- First floor slab completed
- Column raising first floor completed
- Second floor slab completed
- Column raising second floor 100% completed
- Third floor slab 50% completed
Work as of 28th Jan.2022
- Earth filling completed
- Piling works 100% completed
- Pile caps 65% completed
- Ground floor column raising work 80% completed
- Sump tank completed
- Ground floor lift pit completed
- Ground floor stair well shuttering started
- Compaction of ground floor 60% completed
- First floor slab shuttering work started
- Grade beam 60% completed
- Work slow down due to omicron
Work as of 13.04.21 to 20.06.21
Lockdown and containment zone restrictions
No work done