Work Status

November 2022
  • 7th Floor slab in progress 35% completed – centering and shuttering
  • Sixth floor slab concrete completed
  • Column raising concrete in progress 50
  • Fifth floor slab concrete completed
  • Fourth floor slab concrete completed
  • Third floor slab 100% completed
  • Second floor slab completed
  • Column raising second floor 100% completed
  • First floor slab completed
  • Column raising first floor completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • Earth filling¬†completed
October 2022
  • Sixth floor slab centering and shuttering in progress 40%
  • Column raising concrete in progress 50
  • Fifth floor slab concrete completed
  • Fourth floor slab concrete completed
  • Third floor slab 100% completed
  • Second floor slab completed
  • Column raising second floor 100% completed
  • First floor slab completed
  • Column raising first floor completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • Earth filling completed
September 2022
  • Fifth floor slab centering and shuttering in progress 60 percentage completed
  • Fourth floor slab concrete completed
  • Third floor slab 100% completed
  • Second floor slab completed
  • First floor slab completed
  • 4 All pile foundation work completed
  • Sump tank work completed
  • Earth filling completed
  • Column raising ground floor completed
  • Column raising first floor completed
  • Column raising second floor 100% completed
Work status as of 18th August 2022
  1. Fourth floor slab shuttering and centering works in progress 50% complete.
  2. Earth filling completed
  3. All pile foundation work completed
  4. Sump tank work completed
  5. Column raising ground floor completed
  6. First floor slab completed
  7. Column raising first floor completed
  8. Second floor slab completed
  9. Column raising second floor 100% completed
  10. Third floor slab 100% completed
Work as of 7th July 2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. Column raising ground floor completed
  5. First floor slab completed
  6. Column raising first floor completed
  7. Second floor slab completed
  8. Column raising second floor 100% completed
  9. Third floor slab 50% completed
Work as of 7th June 2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. Column raising ground floor completed
  5. First floor slab completed
  6. Column raising first floor completed
  7. Second floor slab 70% completed

8.column raising second floor 25% completed

Work as of 9th May 2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. First floor slab 100% concrete completed
  5. Column raising ground floor 100% completed
  6. Column raising first floor 100% completed
  7. Second floor slab 25% completed
Work as of 21st April 2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. First floor slab 100% concrete completed
  5. Column raising ground floor 100% completed
  6. Column raising first floor 60% completed
Work as of 8th March 2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. First floor slab 30% concrete completed
  5. First floor slab second half area shuttering work started
  6. Column raising ground floor 95% completed
Work as of 25th Feb.2022
  1. Earth filling completed
  2. All pile foundation work completed
  3. Sump tank work completed
  4. Main stair first landing concrete done
  5. First floor slab half portion shuttering completed
  6. Steel work for first floor slab started
  7. Ground floor lift wall raised
  8. Column raising 95% completed
Work as of 28th Jan.2022
  1. Earth filling completed
  2. Piling works 100% completed
  3. Pile caps 65% completed
  4. Ground floor column raising work 80% completed
  5. Sump tank completed
  6. Ground floor lift pit completed
  7. Ground floor stair well shuttering started
  8. Compaction of ground floor 60% completed
  9. First floor slab shuttering work started
  10. Grade beam 60% completed
  11. Work slow down due to omicron
Work as of 32st Dec.2021
  1. Earth filling completed
  2. Piling works 100% completed
  3. Sump tank work 100% completed
  4. Lift wall shuttering upto ff.lvl completed
  5. Ground floor columns raising 30% completed
Work as of 3rd Nov.2021
  1. Earth filling completed
  2. Piling works 100% completed
  3. Grade beams work 10% completed
  4. Sump tank work 50% completed
  5. Pile cap concreting work in progress 50% completed
  6. Ground floor columns raising 15% completed
Work as of 20th Oct.2021
  1. Earth filling completed
  2. Piling works 100% completed
  3. Pile cap concreting work in progress 25% completed
Work as of 19th Sept.2021
  1. Earth filling completed
  2. Piling works 100% completed
  3. Pile cap earthwork started
  4. Pile chipping work started
  5. Pile cap shuttering and steel works started
Work as of 12th Aug.2021
  1. Earth filling completed
  2. Piling works 80% completed
  3. Work not in full swing due to covid -19 pandamic
Work as of 28th July 2021
  1. Earth filling completed
  2. Piling 40% completed
  3. Work not in full swing due to covid -19 pandamic
Work as of 13.04.21 to 20.06.21

Lockdown and containment zone restrictions
No work done

Work as of 5th April. 2021
  1. Earth filling completed
  2. Pile load test
  3. Work not in full swing due to covid -19 pandamic
Work as of 8th March. 2021
  1. Borewell completed
  2. Earth filling completed
  3. Test pile work conducted
  4. Work not in full swing due to covid -19 pandamic
Work as of 12th Feb. 2021
  1. Bhoomi pooja
  2. Site office work completed
  3. Cement shed work completed
  4. Work not in full swing due to covid -19 pandamic
Work as of 9th Jan. 2021
  1. Site clearance
  2. Soil test
  3. Earth filling started
  4. Work not in full swing due to Covid -19 pandemic