WORK STATUS – MARCH 2026
- Earth Works completed.
- Bore Well Works completed.
- Piling work completed.
- Earth work excavation, Pile foundation and Retaining wall of sump tank work completed
- Pile Chipping completed
- Pile cap foundation work completed
- Basement Floor Grade beam work completed
- Basement floor grade slab – 100% completed
- Sump Tank R.C.C Work completed
- Lift pit and its retaining wall work at Basement floor completed.
- Basement floor column and shear wall work completed
- Basement floor to ground floor fire staircase completed
- Basement floor to ground floor ramp work completed
- Ground floor RCC slab work completed
- Basement floor to Ground floor Main staircase completed
- Basement Floor building retaining wall work completed
- First Floor slab R.C.C work 50% completed
- First Floor slab 2nd portion shuttering work 50% completed
- Ground floor to first floor ramp work completed
- Ground Floor Column and Shear wall work completed
- Ground floor to First floor Fire staircase 100% completed
- West side Compound Retaining wall work 95% completed
- East side Compound Retaining wall work 60% completed
- East side Primary Treatment Plant (for sewage) RCC work in progress