WORK STATUS – JAN & FEB 2025
- Earth filling completed
- All pile foundation work completed
- Sump tank work completed
- Sump tank plastering complete up to fireroom
- GF to 17th floor column raising completed
- 1st to 16th floor slab centering and shuttering completed
- 1st to 16th floor slab concrete completed
- Terrace roof slab column rising completed
- Terrace roof slab concrete completed
- Stair roof slab completed
- Overhead tank completed
MASONRY WORKS
- 3rd to 16th floor apartment ceiling plastering completed
- 3rd to 16th floor block masonry completed
- Terrace parapet block masonry work completed
- 3rd to 16th floor wall plastering completed
- 2nd to 1st floor block masonry completed
- Ground floor block masonry completed
- Yard Work – 100% completed
MASONRY WORKS – OUTSIDE PLASTERING
- South Side – ABC Outside
South side external wall plastering from 3rd to 17th floor completed
Ground floor to 3rd floor – 100% completed
- East Side
A, Fire Stair, F type Apartment from 3rd to 17th floor completed
Ground floor to 3rd floor – 100% completed
- North Side
D,E,F type Apartment from 3rd to 17th floor completed
Ground floor to 3rd floor – 100% completed
- West Side
C, D Type – 100% of the outside area completed
Ground floor to 3rd floor – 100% completed
ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING
- Electrical work 3rd to 16th floor – completed
- Electrical work 2nd and 1st floor –completed
- Electrical work on Ground floor – completed
ELECTRICAL WORKS – SWITCH BOX FIXING
- Switch box 17th to ground floor – 100% completed
PLUMBING WORKS
- Plumbing work 3rd to 16th floor – completed.
- Plumbing works on 2nd floor – 100% completed
- Plumbing works on 1st floor – 100% completed
- Plumbing works on Ground floor – 100% completed
- CP and Sanitary fittings 16th to 7th Floor – 100% completed
- CP and Sanitary fittings 6th to ground Floor – 98% completed
WATERPROOFING WORKS
- 3rd to 16th floor waterproofing completed
- Terrace floor – 100% completed
FIRE AND SAFETY WORK
- 3rd to 16th floor fire and safety work completed
- 2nd floor fire and safety work 100% completed
- 1st floor fire and safety work 100% completed
- Ground floor fire and safety work 100% completed
TILE WORK
- 3rd floor 3 F apartment toilet wall and floor tile work completed
- 16 th to 4th floor apartments, passage, staircase – 100% completed
- 3rd floor apartments, passage, staircase – 100% completed
- 2nd floor passage, staircase – 100% completed
- 1st floor passage, staircase – 100% completed
- Ground floor passage, staircase – 100% completed
PAINTING WORK
- Putty work – 17th floor to 1st floor – 100% completed
- Interior Emulsion work 1st coat paint – 16th floor to 3rd floor – 100% completed
- Interior Emulsion work 2nd coat paint: –
16th floor to 3rd floor – 85% completed
16th to 4th floor Passage & Common area – 100% completed
- Interior Emulsion work 1st coat paint – 2nd floor to ground floor – 95% completed
- Interior Emulsion work 2nd coat paint – 2nd floor to ground floor – 80% completed
- Handrail enamel work – 17th floor to Ground floor – 100% completed
- Outside Texture work – North side – 100% completed
- Outside Texture work – East side – 100% completed
- Outside Texture work – South side – 100% completed
- Outside Texture work – West side – 100% completed
- Exterior Emulsion – North side – 100% completed
- Exterior Emulsion – East side – 100% completed
- Exterior Emulsion – South side – 100% completed
- Exterior Emulsion – West side – 100% completed
ALUMINIUM WORK
- 16th floor to 3rd apartments work – 100% completed
- 2nd to ground floor work – 100% completed
DOOR WORK
- 16th floor apartments work – 100% completed
- 15th to 7th floor apartments work – 100% completed
- 6th to 3rd floor apartments work – 100% completed
ELECTRICAL, FIRE, RAMP WORKS, MINI THEATRE AND OTHER WORKS
- Ramp Work – 100% completed
- Mini Theatre – 100% completed
- Duct Door – 100% completed
- Stilling Chamber – 100% completed
- Front Gate Structure – 80% completed
- Compound Wall – 100% completed
- Drain – 100% completed
- Yard Interlock work – 60% completed
- We have received the Energization certificate from Kerala State Electrical Inspectorate for getting electrical connection from KSEB for all the Apartments.
- Both the Lifts are fully functional.
- Water Treatment has commissioned and running 24 hours. Water tested and found satisfactory for domestic purposes.
- Fire Inspection completed and expecting the final NOC from Fire Department.
- Kerala Water Authority connection sanctioned. The Civil works, Road cutting works and other allied will commence shortly.