WORK STATUS – NOVEMBER 2025
- Earth Works completed.
- Bore Well Works completed.
- Piling work completed.
- Earth work excavation, Pile foundation and Retaining wall of sump tank
work completed - Pile cap foundation work 1 st half completed
- Grade beam work- 1 st half completed
- Basement floor grade slab – 1 st half completed
- Pile cap foundation work – 2 nd half 40% completed
- Final Excavation for Balance pile cap work in progress – 75% completed
- Pile chipping in progress – 75% completed
- Lift pit and its retaining wall at Basement floor completed.
- Basement floor ramp to ground floor work 50% completed
- Basement floor to ground floor fire staircase 50% completed
- Ground floor slab shuttering work in progress.