WORK STATUS – SEPTEMBER 2024
- Earth filling completed
- All pile foundation work completed
- Sump tank work completed
- Sump tank plastering complete up to fireroom
- GF to 17th floor column raising completed
- 1st to 16th floor slab centering and shuttering completed
- 1st to 16th floor slab concrete completed
- Terrace roof slab column rising completed
- Terrace roof slab concrete completed
- Stair roof slab completed
- Overhead tank completed
MASONRY WORKS
- 3rd to 16th floor apartment ceiling plastering completed
- 3rd to 16th floor block masonry completed
- Terrace parapet block masonry work completed
- 3rd to 16th floor wall plastering completed
- 2nd to 1st floor block masonry completed
- Ground floor block masonry completed
- Ground floor Yard Work in progress
MASONRY WORKS – OUTSIDE PLASTERING
- South Side – ABC Outside
South side external wall plastering from 3rd to 17th floor completed
Ground floor to 3rd floor – 100% completed
- East Side
A, Fire Stair, F type Apartment from 3rd to 17th floor completed
Ground floor to 3rd floor – 100% completed
- North Side
D,E,F type Apartment from 3rd to 17th floor completed
Ground floor to 3rd floor – 90% completed
- West Side
C,D Type – 100% of the outside area completed
Ground floor to 3rd floor – 90% completed
ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING
- Electrical work 3rd to 16th floor – completed
- Electrical work 2nd and 1st floor – 90% completed
- Electrical work on Ground floor – 70% completed
ELECTRICAL WORKS – SWITCH BOX FIXING
- Switch box 16th and 8th floor – 100% completed
PLUMBING WORKS
- Plumbing work 3rd to 16th floor – completed.
- Plumbing works on 2nd floor – 90% completed
- Plumbing works on 1st floor – 90% completed
- Plumbing works on Ground floor – 45% completed
WATERPROOFING WORKS
- 3rd to 15th floor waterproofing completed
- 16th floor waterproofing – 100% completed
- Terrace floor – 100% completed
FIRE AND SAFETY WORK
- 3rd to 16th floor fire and safety work completed
- 2nd floor fire and safety work 100% completed
- 1st floor fire and safety work 100% completed
- Ground floor fire and safety work 90% completed
TILE WORK
- 3rd floor 3 F apartment toilet wall and floor tile work completed
- 16th floor apartments, passage, staircase – 100% completed
- 15th floor apartments, passage, staircase – 100% completed
- 14th floor apartments, passage, staircase – 100% completed
- 13th floor apartments, passage, staircase – 100% completed
- 12th floor apartments, passage, staircase – 100% completed
- 11th floor apartments, passage, staircase – 100% completed
- 10th floor apartments, passage, staircase – 100% completed
- 9th floor apartments, passage, staircase – 100% completed
- 8th floor apartments, passage, staircase – 100% completed
- 7th floor apartments, passage, staircase – 100% completed
- 6th floor apartments, passage, staircase – 100% completed
- 5th floor apartments, passage, staircase – 100% completed
- 4th floor apartments, passage, staircase – 100% completed
- 3rd floor apartments, passage, staircase – 90% completed
- 2nd floor passage, staircase – 100% completed
- 1st floor passage, staircase – 100% completed
- Ground floor passage, staircase – 50% completed
PAINTING WORK
- Putty work – 17th floor to 1st floor – 100% completed
- Interior Emulsion work 1st coat paint – 16th floor to 7th floor – 100% completed
- Handrail enamel work – 17th floor to Ground floor – 100% completed
- Outside Texture work – North side – 100% completed
- Outside Texture work – East side – 100% completed
- Outside Texture work – South side – 100% completed
- Outside Texture work – West side – 50% completed
- Exterior Emulsion – North side – 100% completed
- Exterior Emulsion – East side – 100% completed
- Exterior Emulsion – South side – 100% completed
- Exterior Emulsion – West side – 70% completed
ALUMINIUM WORK
- 16th floor apartments work – 100% completed
- 15th to 3rd floor apartments work – 95% completed
DOOR WORK
- 16th floor apartments work – 100% completed
- 15th to 7rd floor apartments work – 95% completed
- 6th to 3rd floor apartments work – 60% completed