Current Work Status

RERA: K-RERA/PRJ/TVM/096/2024

Type: 2 & 3 BHK Apartments

Last updated: June 2026

June 2026

  • Earth Works completed.
  • Bore Well Works completed.
  • Piling work completed.
  • Earth work excavation, Pile foundation and Retaining wall of sump tank work completed
  • Pile Chipping completed
  • Pile cap foundation work completed
  • Basement Floor Grade beam work completed
  • Basement floor grade slab completed
  • Sump Tank R.C.C Work completed
  • Sewage Stilling Chamber RCC work 65% completed.
  • Lift pit and its retaining wall work at Basement floor completed.
  • Basement floor column and shear wall work completed
  • Basement floor to ground floor fire staircase completed
  • Basement floor to ground floor ramp work completed
  • Basement floor to Ground floor Main staircase completed
  • Basement floor to Ground floor Fire staircase completed
  • Basement Floor building retaining wall work completed
  • Ground floor RCC slab work completed
  • Ground Floor Column and Shear wall work completed
  • Ground floor to First floor Fire staircase completed
  • Ground floor to First floor Main staircase completed
  • Ground floor to first floor ramp work completed
  • First Floor slab R.C.C work completed
  • First Floor Columns and Shear Wall completed
  • First Floor to Second Floor Ramp completed
  • First Floor to Second Floor Fire Staircase completed
  • First Floor to Second Floor Main Staircase completed
  • Second Floor slab RCC work completed
  • Second Floor Columns and shear wall completed
  • Second Floor to Third Floor Fire Staircase – 65% completed
  • Second Floor to Third Floor Main Staircase – 75% completed
  • Third Floor Slab shuttering & steel work in progress – 40% completed
  • West side Compound Retaining wall work 95% completed
  • East side Compound Retaining wall work 65% completed



May 2026

  • Earth Works completed.
  • Bore Well Works completed.
  • Piling work completed.
  • Earth work excavation, Pile foundation and Retaining wall of sump tank work completed
  • Pile Chipping completed
  • Pile cap foundation work completed
  • Basement Floor Grade beam work completed
  • Basement floor grade slab completed
  • Sump Tank R.C.C Work completed
  • Lift pit and its retaining wall work at Basement floor completed.
  • Basement floor column and shear wall work completed
  • Basement floor to ground floor fire staircase completed
  • Basement floor to ground floor ramp work completed
  • Basement floor to Ground floor Main staircase completed
  • Basement floor to Ground floor Fire staircase completed
  • Basement Floor building retaining wall work completed
  • Ground floor RCC slab work completed
  • Ground Floor Column and Shear wall work completed
  • Ground floor to First floor Fire staircase completed
  • Ground floor to First floor Main staircase completed
  • Ground floor to first floor ramp work completed
  • First Floor slab R.C.C work completed
  • First Floor Columns and Shear Wall completed
  • First Floor to Second Floor Ramp completed
  • First Floor to Second Floor Fire Staircase completed
  • First Floor to Second Floor Main Staircase completed
  • Second Floor slab RCC work  – 65% completed
  • Second Floor Slab balance shuttering work in progress – 40% completed
  • West side Compound Retaining wall work 95% completed
  • East side Compound Retaining wall work 65% completed

 

April 2026

  • Earth Works completed.
  • Bore Well Works completed.
  • Piling work completed.
  • Earth work excavation, Pile foundation and Retaining wall of sump tank work completed
  • Pile Chipping completed
  • Pile cap foundation work completed
  • Basement Floor Grade beam work completed
  • Basement floor grade slab – 100% completed
  • Sump Tank R.C.C Work completed
  • Lift pit and its retaining wall work at Basement floor completed.
  • Basement floor column and shear wall work completed
  • Basement floor to ground floor fire staircase completed
  • Basement floor to ground floor ramp work completed
  • Ground floor RCC slab work completed
  • Basement floor to Ground floor Main staircase completed
  • Basement Floor building retaining wall work completed
  • First Floor slab R.C.C work completed
  • Ground floor to first floor ramp work completed
  • Ground Floor Column and Shear wall work completed
  • Ground floor to First floor Fire staircase 100% completed
  • West side Compound Retaining wall work 95% completed
  • East side Compound Retaining wall work 60% completed
  • East side Primary Treatment Plant (for sewage) RCC work in progress – 25% completed
  • First Floor Column Steel work in progress

 

March 2026

  • Earth Works completed.
  • Bore Well Works completed.
  • Piling work completed.
  • Earth work excavation, Pile foundation and Retaining wall of sump tank work completed
  • Pile Chipping completed
  • Pile cap foundation work completed
  • Basement Floor Grade beam work completed
  • Basement floor grade slab – 100% completed
  • Sump Tank R.C.C Work completed
  • Lift pit and its retaining wall work at Basement floor completed.
  • Basement floor column and shear wall work completed
  • Basement floor to ground floor fire staircase completed
  • Basement floor to ground floor ramp work completed
  • Ground floor RCC slab work completed
  • Basement floor to Ground floor Main staircase completed
  • Basement Floor building retaining wall work completed
  • First Floor slab R.C.C work 50% completed
  • First Floor slab 2nd portion shuttering work 50% completed
  • Ground floor to first floor ramp work completed
  • Ground Floor Column and Shear wall work completed
  • Ground floor to First floor Fire staircase 100% completed
  • West side Compound Retaining wall work 95% completed
  • East side Compound Retaining wall work 60% completed
  • East side Primary Treatment Plant (for sewage) RCC work in progress

 

February 2026

  • Earth Works completed.
  • Bore Well Works completed.
  • Piling work completed.
  • Earth work excavation, Pile foundation and Retaining wall of sump tank work completed
  • Pile Chipping completed
  • Pile cap foundation work completed
  • Basement Floor Grade beam work completed
  • Basement floor grade slab – 100% completed
  • Sump Tank R.C.C Work completed
  • Lift pit and its retaining wall work at Basement floor completed.
  • Basement floor column and shear wall work – 95% completed
  • Basement floor to ground floor fire staircase completed
  • Basement floor to ground floor ramp work completed
  • Ground floor RCC slab work 50% completed
  • Ground floor slab shuttering work 2nd Half work in progress
  • Basement floor to Ground floor Main staircase 80% completed
  • Basement Floor building retaining wall work completed
  • First Floor slab R.C.C work 50% completed
  • Ground floor to first floor ramp work 100% completed
  • Ground Floor Column work 50% completed
  • Ground floor to First floor Fire staircase 100% completed
  • West side Compound Retaining wall work 60% completed
  • East side Compound Retaining wall work 60% completed

 

January 2026

  • Earth Works completed.
  • Bore Well Works completed.
  • Piling work completed.
  • Earth work excavation, Pile foundation and Retaining wall of sump tank work completed
  • Pile Chipping completed
  • Pile cap foundation work completed
  • Basement Floor Grade beam work completed
  • Basement floor grade slab – 90% completed
  • Sump Tank R.C.C Work completed
  • Lift pit and its retaining wall work at Basement floor completed.
  • Basement floor column and shear wall work – 95% completed
  • Basement floor to ground floor fire staircase completed
  • Basement floor to ground floor ramp work completed
  • Ground floor RCC slab work 50% completed
  • Ground floor slab shuttering work 2nd Half work in progress
  • Basement floor to Ground floor Main staircase 80% completed
  • Basement Floor building retaining wall work completed
  • First Floor slab shuttering and steel work 50% completed
  • Ground floor to first floor ramp work 70% completed
  • Ground Floor Column work 50% completed
  • Ground floor to First floor Fire staircase 60% completed
  • West side Compound Retaining wall work 60% completed
  • East side Compound Retaining wall work 60% completed

 

December 2025

  • Earth Works completed.
  • Bore Well Works completed.
  • Piling work completed.
  • Earth work excavation, Pile foundation and Retaining wall of sump tank work completed
  • Pile cap foundation work 1st half completed
  • Basement Floor Grade beam work- 1st half completed
  • Basement floor grade slab – 1st half completed
  • Pile cap foundation work – 2nd half 80% completed
  • Final Excavation for Balance pile cap work in progress – 80% completed
  • Pile chipping in progress – 90% completed
  • Lift pit and its retaining wall work at Basement floor completed.
  • Basement floor to ground floor ramp work 100% completed
  • Basement floor column work – 50% completed
  • Basement floor to ground floor fire staircase 100% completed
  • Ground floor slab work – 50% completed
  • Basement Floor Grade beam work – 2nd Half 50% completed
  • Basement Floor building retaining wall work in progress
  • Ground Floor to first floor ramp work – 50% completed
  • Ground Floor Column work 30% completed
  • Ground floor to First floor Fire staircase 60% completed

 

November 2025

  • Earth Works completed.
  • Bore Well Works completed.
  • Piling work completed.
  • Earth work excavation, Pile foundation and Retaining wall of sump tank work completed
  • Pile cap foundation work 1st half completed
  • Grade beam work- 1st half completed
  • Basement floor grade slab – 1st half completed
  • Pile cap foundation work – 2nd half 40% completed
  • Final Excavation for Balance pile cap work in progress – 75% completed
  • Pile chipping in progress – 75% completed
  • Lift pit and its retaining wall at Basement floor completed.
  • Basement floor ramp to ground floor work 50% completed
  • Basement floor to ground floor fire staircase 50% completed
  • Ground floor slab shuttering work in progress.

 

Ready to Find Your Home?

Book a Visit to Cordial Vajram

Our advisors will arrange a personalised site tour at your convenience and guide you through pricing, floor plans, and payment options.

© 2026 Cordial Developers Pvt. Ltd. All Rights Reserved. · RERA Registered.

Crafted by Medowa Global