January 2024

WORK STATUS – January 2024

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 13th to 14th floor column raising completed
  • 14th floor slab concrete completed
  • 14th to 15th column raising completed
  • 15th floor slab concrete completed
  • 15th to 16th column raising completed
  • 16th floor slab concrete completed
  • Terrace roof slab column rising completed
  • Terrace roof slab concrete completed
  • Stair roof slab completed
  • Overhead tank completed

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering completed
  • 11th floor apartment ceiling plastering completed
  • 12th floor apartment ceiling plastering completed
  • 13th floor apartment ceiling plastering completed
  • 14th floor apartment ceiling plastering completed
  • 15th floor apartment ceiling plastering completed
  • 16th floor apartment ceiling plastering complete
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 10th floor block masonry completed
  • 11th floor block masonry completed
  • 12th floor block masonry completed
  • 13th floor block masonry completed
  • 14th floor block masonry completed
  • 15th floor block masonry completed
  • 16th floor block masonry completed
  • Terrace parapet block masonry work completed
  • 3rd floor wall plastering completed
  • 4th floor wall plastering work completed
  • 5th floor wall plastering completed
  • 6th floor wall plastering completed
  • 7th floor wall plastering completed
  • 8th floor wall plastering completed
  • 9th floor wall plastering completed
  • 10th floor wall plastering completed
  • 11th floor wall plastering completed
  • 12th floor wall plastering completed
  • 13th floor wall plastering completed
  • 14th floor wall plastering completed
  • 15th floor wall plastering completed
  • 16th floor wall plastering completed

MASONRY WORKS – OUTSIDE PLASTERING

  • South Side – ABC Outside

South side external wall plastering from 3rd to 17th floor completed

  • East Side

A, Fire Stair, F type Apartment from 3rd to 17th floor completed

  • North Side

D, E, F Type – 30% of the outside area completed

 ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor-completed
  • Electrical work-5th floor –completed
  • Electrical work- 6th floor –completed
  • Electrical work- 7th floor – completed
  • Electrical work- 8th floor – complete
  • Electrical work- 9th floor – completed
  • Electrical work- 10th floor – completed
  • Electrical work- 11th floor – complete
  • Electrical work- 12th floor – completed
  • Electrical work- 13th floor –completed
  • Electrical work- 14th floor –completed
  • Electrical work- 15th floor –completed
  • Electrical work- 16th floor –completed

PLUMBING WORKS – PIPELINE WORKS & PRESSURE TESTING WORKS

  • Plumbing work 3th floor – completed.
  • Plumbing work 4th floor – completed
  • Plumbing work 5th floor – completed
  • Plumbing work 6th floor – completed
  • Plumbing work 7th floor – completed
  • Plumbing work 8th floor – completed
  • Plumbing work 9th floor – completed
  • Plumbing work 10th floor – completed
  • Plumbing work 11th floor – completed
  • Plumbing work 12th floor – completed
  • Plumbing work 13th floor – completed
  • Plumbing work 14th floor – completed
  • Plumbing work 15th floor – completed
  • Plumbing work 16th floor – 50% complete

WATERPROOFING WORKS

  • 3rd floor waterproofing completed
  • 4th floor waterproofing completed
  • 5th floor waterproofing completed
  • 6th floor waterproofing completed
  • 7th floor waterproofing completed
  • 8th floor waterproofing completed
  • 9th floor waterproofing completed
  • 10th floor waterproofing completed
  • 11th floor waterproofing completed
  • 12th floor waterproofing completed
  • 13th floor waterproofing completed
  • 14th floor waterproofing – 85% completed
  • 15th floor waterproofing – 85% completed
  • 16th floor waterproofing – 85% completed

FIRE AND SAFETY WORK

  • 3rd floor fire and safety work completed
  • 4th floor fire and safety work completed
  • 5th floor fire and safety work completed
  • 6th floor fire and safety work completed
  • 7th floor fire and safety work completed
  • 8th floor fire and safety work completed
  • 9th floor fire and safety work completed
  • 10th floor fire and safety work completed
  • 11th floor fire and safety work completed
  • 12th floor fire and safety work completed
  • 13th floor fire and safety work completed
  • 14th floor fire and safety work 75% complete
  • 15th floor fire and safety work 75% complete
  • 16th floor fire and safety work 75% complete

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor tile work completed
  • 16th floor – 35% complete

PAINTING WORK

  • Putty and painting work on 3F completed
  • 3rd floor putty 1st coat completed
  • 4th floor putty 1st coat completed
  • 5th floor putty 1st coat 80% complete
  • 6th floor putty 1st coat completed
  • 7th floor putty 1st coat completed
  • 8th floor putty 1st coat 50% complete
  • 9th floor putty 1st coat completed
  • 10th floor putty 1st coat completed
  • 11th floor putty 1st coat completed
  • 12th floor putty 1st coat completed
  • 13th floor putty 1st coat completed
  • 14th floor putty 1st coat completed
  • 15th floor putty 1st coat completed
  • 16th floor putty 1st coat 50% complete