May 2023
  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Column raising ground floor completed
  • First floor slab completed
  • Column raising first floor completed
  • Second floor slab completed
  • Column raising second floor completed
  • Third floor slab completed
  • Column raising third floor completed
  • Fourth floor slab completed
  • Column raising fourth floor completed
  • Fifth floor slab completed
  • Column raising sixth slab completed
  • Third floor apartment type F, E and D ceiling plastering completed
  • Sump tank plastering complete up to fireroom
  • 6th floor slab centering and shuttering completed
  • 6th floor slab concrete completed
  • 6th to 7th  column raising completed
  • 7th floor slab centering and shuttering completed
  • 7th floor slab concrete completed
  • 7th to 8th  floor column raising completed
  • 8th floor slab centering and shuttering completed
  • 8th floor slab concrete completed
  • 8th to 9th floor column raising completed
  • 9th floor slab centering and shuttering completed
  • 9th floor slab concrete completed
  • 9th to 10th floor column raising completed
  • 10th floor slab concrete completed
  • 10th to 11th floor column raising completed
  • 11th floor slab concrete completed
  • 11th to 12th floor column raising completed
  • 12th floor slab concrete completed
  • 12th to 13th floor column raising completed
  • 13th floor slab concrete completed
  • 14th floor part 1st slab concrete completed
  • 14th floor part 2nd shuttering work completed
  • 14th to 15th part 1st column reinforcement completed

MASONRY WORKS

  • 3rd floor apartment ceiling plastering completed
  • 4th floor apartment ceiling plastering completed
  • 5th floor apartment ceiling plastering completed
  • 6th floor apartment ceiling plastering completed
  • 7th floor apartment ceiling plastering completed
  • 8th floor apartment ceiling plastering completed
  • 9th floor apartment ceiling plastering completed
  • 10th floor apartment ceiling plastering -60% completed
  • 3rd floor block masonry completed
  • 4th floor block masonry completed
  • 5th floor block masonry completed
  • 6th floor block masonry completed
  • 7th floor block masonry completed
  • 8th floor block masonry completed
  • 9th floor block masonry completed
  • 3rd floor wall plastering completed
  • 4 A and 4 B wall plastering work in progress – 50% completed

ELECTRICAL WORKS

  • Electrical work 3rd floor – completed
  • Electrical work 4th floor-completed
  • Electrical work-5th floor –box fixing work in progress

PLUMBING WORKS

  • Plumbing work 3F Apartment wall chasing and pipe laying completed.
  • Plumbing work 3A,3B,3C,3D&3E apartment in progress 20%