January 2023
  • 9th floor slab shuttering and centering work in progress – 50% completed
  • 8th to 9th floor column raising -75% completed
  • 8th floor slab concrete – completed
  • Masonry work in progress – ceiling plastering & block work – 40%
  • 7th Floor slab concrete completed
  • Sixth floor slab concrete completed
  • Fifth floor slab concrete completed
  • Fourth floor slab concrete completed
  • Third floor slab concrete completed
  • Second floor slab concrete completed
  • First floor slab concrete completed
  • Column raising first floor completed
  • All pile foundation works completed
  • Sump tank works completed
  • Column raising ground floor completed
  • Earth filling¬†completed