May 2023
- Earth filling completed
- All pile foundation work completed
- Sump tank work completed
- Column raising ground floor completed
- First floor slab completed
- Column raising first floor completed
- Second floor slab completed
- Column raising second floor completed
- Third floor slab completed
- Column raising third floor completed
- Fourth floor slab completed
- Column raising fourth floor completed
- Fifth floor slab completed
- Column raising sixth slab completed
- Third floor apartment type F, E and D ceiling plastering completed
- Sump tank plastering complete up to fireroom
- 6th floor slab centering and shuttering completed
- 6th floor slab concrete completed
- 6th to 7th column raising completed
- 7th floor slab centering and shuttering completed
- 7th floor slab concrete completed
- 7th to 8th floor column raising completed
- 8th floor slab centering and shuttering completed
- 8th floor slab concrete completed
- 8th to 9th floor column raising completed
- 9th floor slab centering and shuttering completed
- 9th floor slab concrete completed
- 9th to 10th floor column raising completed
- 10th floor slab concrete completed
- 10th to 11th floor column raising completed
- 11th floor slab concrete completed
- 11th to 12th floor column raising completed
- 12th floor slab concrete completed
- 12th to 13th floor column raising completed
- 13th floor slab concrete completed
- 14th floor part 1st slab concrete completed
- 14th floor part 2nd shuttering work completed
- 14th to 15th part 1st column reinforcement completed
MASONRY WORKS
- 3rd floor apartment ceiling plastering completed
- 4th floor apartment ceiling plastering completed
- 5th floor apartment ceiling plastering completed
- 6th floor apartment ceiling plastering completed
- 7th floor apartment ceiling plastering completed
- 8th floor apartment ceiling plastering completed
- 9th floor apartment ceiling plastering completed
- 10th floor apartment ceiling plastering -60% completed
- 3rd floor block masonry completed
- 4th floor block masonry completed
- 5th floor block masonry completed
- 6th floor block masonry completed
- 7th floor block masonry completed
- 8th floor block masonry completed
- 9th floor block masonry completed
- 3rd floor wall plastering completed
- 4 A and 4 B wall plastering work in progress – 50% completed
ELECTRICAL WORKS
- Electrical work 3rd floor – completed
- Electrical work 4th floor-completed
- Electrical work-5th floor –box fixing work in progress
PLUMBING WORKS
- Plumbing work 3F Apartment wall chasing and pipe laying completed.
- Plumbing work 3A,3B,3C,3D&3E apartment in progress 20%