May 2024
WORK STATUS – May 2024
- Earth filling completed
- All pile foundation work completed
- Sump tank work completed
- Sump tank plastering complete up to fireroom
- GF to 17th floor column raising completed
- 1st to 16th floor slab centering and shuttering completed
- 1st to 16th floor slab concrete completed
- Terrace roof slab column rising completed
- Terrace roof slab concrete completed
- Stair roof slab completed
- Overhead tank completed
MASONRY WORKS
- 2nd floor plastering 50% completed
- 3rd to 16th floor apartment ceiling plastering completed
- 3rd to 16th floor block masonry completed
- Terrace parapet block masonry work completed
- 3rd to 16th floor wall plastering completed
MASONRY WORKS – OUTSIDE PLASTERING
- South Side – ABC Outside
South side external wall plastering from 3rd to 17th floor completed
- East Side
A, Fire Stair, F type Apartment from 3rd to 17th floor completed
- North Side
D,E,F type Apartment from 3rd to 17th floor completed
- West Side
C,D Type – 90% of the outside area completed
ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING
- Electrical work 3rd to 16th floor – completed
PLUMBING WORKS
- Plumbing work 3rd to 16th floor – completed.
WATERPROOFING WORKS
- 3rd to 15th floor waterproofing completed
- 16th floor waterproofing – 100% completed
- Terrace floor – 100% completed
FIRE AND SAFETY WORK
- 3rd to 16th floor fire and safety work completed
TILE WORK
- 3rd floor 3 F apartment toilet wall and floor tile work completed
- 16th floor apartments, passage, staircase – 85% completed
- 15th floor apartments, passage, staircase – 90% completed
- 14th floor apartments, passage, staircase – 90% completed
- 13th floor apartments, passage, staircase – 95% completed
- 12th floor apartments, passage, staircase – 90% completed
- 11th floor apartments, passage, staircase – 80% completed
- 10th floor apartments, passage, staircase – 75% completed
- 9th floor apartments, passage, staircase – 65% completed
- 8th floor apartments, passage, staircase – 55% completed
- 7th floor apartments, passage, staircase – 70% completed
- 6th floor – apartments, passage, staircase- 65% completed
- 5th floor – apartments, passage, staircase -55% completed
- 4th floor – apartments, passage, staircase- 60% completed
- 3rd floor – apartments, passage, staircase- 50% completed
PAINTING WORK
- Putty and painting work on 3F completed
- 3rd to 4th floor putty 1st coat completed
- 5th floor putty 1st coat 80% completed
- 6th to 7th floor putty 1st coat completed
- 8th floor putty 1st coat 50% completed
- 9th to 15th floor putty 1st coat completed
- 16th floor putty 1st coat completed
- 16th and 15th floor A, B – 2nd coat putty completed
- East side outside primer – completed
- South side primer – completed
- North side primer – completed
- Painting interior emulsion 1st coat commenced – In Progress
- Painting exterior emulsion 1st coat commenced – In Progress