March 2024

WORK STATUS – March 2024

  • Earth filling completed
  • All pile foundation work completed
  • Sump tank work completed
  • Sump tank plastering complete up to fireroom
  • GF to 17th floor column raising completed
  • 1st to 16th floor slab centering and shuttering completed
  • 1st to 16th floor slab concrete completed
  • Terrace roof slab column rising completed
  • Terrace roof slab concrete completed
  • Stair roof slab completed
  • Overhead tank completed

MASONRY WORKS

  • 2nd floor plastering 50% completed
  • 3rd to 16th floor apartment ceiling plastering completed
  • 3rd to 16th floor block masonry completed
  • Terrace parapet block masonry work completed
  • 3rd to 16th floor wall plastering completed

MASONRY WORKS – OUTSIDE PLASTERING

  • South Side – ABC Outside

South side external wall plastering from 3rd to 17th floor completed

  • East Side

A, Fire Stair, F type Apartment from 3rd to 17th floor completed

  • North Side

D, E, F type Apartment from 3rd to 17th floor completed

  • West Side

C, D Type – 75% of the outside area completed

 

ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING

  • Electrical work 3rd to 16th floor – completed

PLUMBING WORKS

  • Plumbing work 3rd to 16th floor – completed.

WATERPROOFING WORKS

  • 3rd to 15th floor waterproofing completed
  • 16th floor waterproofing – 90% completed
  • Terrace floor – 80% completed

FIRE AND SAFETY WORK

  • 3rd to 16th floor fire and safety work completed

TILE WORK

  • 3rd floor 3 F apartment toilet wall and floor tile work completed
  • 16th floor – 50% complete
  • 15th floor – 80% complete
  • 14th floor – 75% complete
  • 13th floor – 65% complete
  • 12th floor – 60% complete
  • 11th floor – 70% complete
  • 10th floor – 30% complete

PAINTING WORK

  • Putty and painting work on 3F completed
  • 3rd to 4th floor putty 1st coat completed
  • 5th floor putty 1st coat 80% complete
  • 6th to 7th floor putty 1st coat completed
  • 8th floor putty 1st coat 50% complete
  • 9th to 15th floor putty 1st coat completed
  • 16th floor putty 1st coat 60% complete
  • 16th and 15th floor A, B – 2nd coat putty completed
  • East side outside primer – completed
  • South side primer – completed
  • North side primer – 50% completed