February 2024
WORK STATUS – February 2024
- Earth filling completed
- All pile foundation work completed
- Sump tank work completed
- Column raising ground floor completed
- First floor slab completed
- Column raising first floor completed
- Second floor slab completed
- Column raising second floor completed
- Third floor slab completed
- Column raising third floor completed
- Fourth floor slab completed
- Column raising fourth floor completed
- Fifth floor slab completed
- Column raising sixth slab completed
- Third floor apartment type F, E and D ceiling plastering completed
- Sump tank plastering complete up to fireroom
- 6th floor slab centering and shuttering completed
- 6th floor slab concrete completed
- 6th to 7th column raising completed
- 7th floor slab centering and shuttering completed
- 7th floor slab concrete completed
- 7th to 8th floor column raising completed
- 8th floor slab centering and shuttering completed
- 8th floor slab concrete completed
- 8th to 9th floor column raising completed
- 9th floor slab centering and shuttering completed
- 9th floor slab concrete completed
- 9th to 10th floor column raising completed
- 10th floor slab concrete completed
- 10th to 11th floor column raising completed
- 11th floor slab concrete completed
- 11th to 12th floor column raising completed
- 12th floor slab concrete completed
- 12th to 13th floor column raising completed
- 13th floor slab concrete completed
- 13th to 14th floor column raising completed
- 14th floor slab concrete completed
- 14th to 15th column raising completed
- 15th floor slab concrete completed
- 15th to 16th column raising completed
- 16th floor slab concrete completed
- Terrace roof slab column rising completed
- Terrace roof slab concrete completed
- Stair roof slab completed
- Over head tank completed
MASONRY WORKS
- 3rd floor apartment ceiling plastering completed
- 4th floor apartment ceiling plastering completed
- 5th floor apartment ceiling plastering completed
- 6th floor apartment ceiling plastering completed
- 7th floor apartment ceiling plastering completed
- 8th floor apartment ceiling plastering completed
- 9th floor apartment ceiling plastering completed
- 10th floor apartment ceiling plastering completed
- 11th floor apartment ceiling plastering completed
- 12th floor apartment ceiling plastering completed
- 13th floor apartment ceiling plastering completed
- 14th floor apartment ceiling plastering completed
- 15th floor apartment ceiling plastering completed
- 16th floor apartment ceiling plastering complete
- 3rd floor block masonry completed
- 4th floor block masonry completed
- 5th floor block masonry completed
- 6th floor block masonry completed
- 7th floor block masonry completed
- 8th floor block masonry completed
- 9th floor block masonry completed
- 10th floor block masonry completed
- 11th floor block masonry completed
- 12th floor block masonry completed
- 13th floor block masonry completed
- 14th floor block masonry completed
- 15th floor block masonry completed
- 16th floor block masonry completed
- Terrace parapet block masonry work completed
- 3rd floor wall plastering completed
- 4th floor wall plastering work completed
- 5th floor wall plastering completed
- 6th floor wall plastering completed
- 7th floor wall plastering completed
- 8th floor wall plastering completed
- 9th floor wall plastering completed
- 10th floor wall plastering completed
- 11th floor wall plastering completed
- 12th floor wall plastering completed
- 13th floor wall plastering completed
- 14th floor wall plastering completed
- 15th floor wall plastering completed
- 16th floor wall plastering completed
MASONRY WORKS – OUTSIDE PLASTERING
- South Side – ABC Outside
South side external wall plastering from 3rd to 17th floor completed
- East Side
A, Fire Stair, F type Apartment from 3rd to 17th floor completed
- North Side
D, E, F Type – 50% of the outside area completed
- West Side
C, D Type – 40% of the outside area completed
ELECTRICAL WORKS – WALL CHASING, CONDUIT AND METAL BOX FIXING
- Electrical work 3rd floor – completed
- Electrical work 4th floor-completed
- Electrical work-5th floor –completed
- Electrical work- 6th floor –completed
- Electrical work- 7th floor – completed
- Electrical work- 8th floor – complete
- Electrical work- 9th floor – completed
- Electrical work- 10th floor – completed
- Electrical work- 11th floor – complete
- Electrical work- 12th floor – completed
- Electrical work- 13th floor –completed
- Electrical work- 14th floor –completed
- Electrical work- 15th floor –completed
- Electrical work- 16th floor –completed
PLUMBING WORKS
- Plumbing work 3th floor – completed.
- Plumbing work 4th floor – completed
- Plumbing work 5th floor – completed
- Plumbing work 6th floor – completed
- Plumbing work 7th floor – completed
- Plumbing work 8th floor – completed
- Plumbing work 9th floor – completed
- Plumbing work 10th floor – completed
- Plumbing work 11th floor – completed
- Plumbing work 12th floor – completed
- Plumbing work 13th floor – completed
- Plumbing work 14th floor – completed
- Plumbing work 15th floor – completed
- Plumbing work 16th floor – completed
WATERPROOFING WORKS
- 3rd floor waterproofing completed
- 4th floor waterproofing completed
- 5th floor waterproofing completed
- 6th floor waterproofing completed
- 7th floor waterproofing completed
- 8th floor waterproofing completed
- 9th floor waterproofing completed
- 10th floor waterproofing completed
- 11th floor waterproofing completed
- 12th floor waterproofing completed
- 13th floor waterproofing completed
- 14th floor waterproofing completed
- 15th floor waterproofing – 85% completed
- 16th floor waterproofing – 90% completed
FIRE AND SAFETY WORK
- 3rd floor fire and safety work completed
- 4th floor fire and safety work completed
- 5th floor fire and safety work completed
- 6th floor fire and safety work completed
- 7th floor fire and safety work completed
- 8th floor fire and safety work completed
- 9th floor fire and safety work completed
- 10th floor fire and safety work completed
- 11th floor fire and safety work completed
- 12th floor fire and safety work completed
- 13th floor fire and safety work completed
- 14th floor fire and safety work completed
- 15th floor fire and safety work completed
- 16th floor fire and safety work completed
TILE WORK
- 3rd floor 3 F apartment toilet wall and floor tile work completed
- 16th floor – 40% complete
- 15th floor toilet wall tile laying – 50% complete
- 14th floor toilet tile – 50% complete
- 13th floor toilet wall tile – 50% complete
PAINTING WORK
- Putty and painting work on 3F completed
- 3rd floor putty 1st coat completed
- 4th floor putty 1st coat completed
- 5th floor putty 1st coat 80% complete
- 6th floor putty 1st coat completed
- 7th floor putty 1st coat completed
- 8th floor putty 1st coat 50% complete
- 9th floor putty 1st coat completed
- 10th floor putty 1st coat completed
- 11th floor putty 1st coat completed
- 12th floor putty 1st coat completed
- 13th floor putty 1st coat completed
- 14th floor putty 1st coat completed
- 15th floor putty 1st coat completed
- 16th floor putty 1st coat 60% complete